Accendo Reliability

Your Reliability Engineering Professional Development Site

  • Home
  • About
    • Contributors
    • About Us
    • Colophon
    • Survey
  • Reliability.fm
  • Articles
    • CRE Preparation Notes
    • NoMTBF
    • on Leadership & Career
      • Advanced Engineering Culture
      • ASQR&R
      • Engineering Leadership
      • Managing in the 2000s
      • Product Development and Process Improvement
    • on Maintenance Reliability
      • Aasan Asset Management
      • AI & Predictive Maintenance
      • Asset Management in the Mining Industry
      • CMMS and Maintenance Management
      • CMMS and Reliability
      • Conscious Asset
      • EAM & CMMS
      • Everyday RCM
      • History of Maintenance Management
      • Life Cycle Asset Management
      • Maintenance and Reliability
      • Maintenance Management
      • Plant Maintenance
      • Process Plant Reliability Engineering
      • RCM Blitz®
      • ReliabilityXperience
      • Rob’s Reliability Project
      • The Intelligent Transformer Blog
      • The People Side of Maintenance
      • The Reliability Mindset
    • on Product Reliability
      • Accelerated Reliability
      • Achieving the Benefits of Reliability
      • Apex Ridge
      • Field Reliability Data Analysis
      • Metals Engineering and Product Reliability
      • Musings on Reliability and Maintenance Topics
      • Product Validation
      • Reliability by Design
      • Reliability Competence
      • Reliability Engineering Insights
      • Reliability in Emerging Technology
      • Reliability Knowledge
    • on Risk & Safety
      • CERM® Risk Insights
      • Equipment Risk and Reliability in Downhole Applications
      • Operational Risk Process Safety
    • on Systems Thinking
      • Communicating with FINESSE
      • The RCA
    • on Tools & Techniques
      • Big Data & Analytics
      • Experimental Design for NPD
      • Innovative Thinking in Reliability and Durability
      • Inside and Beyond HALT
      • Inside FMEA
      • Institute of Quality & Reliability
      • Integral Concepts
      • Learning from Failures
      • Progress in Field Reliability?
      • R for Engineering
      • Reliability Engineering Using Python
      • Reliability Reflections
      • Statistical Methods for Failure-Time Data
      • Testing 1 2 3
      • The Manufacturing Academy
  • eBooks
  • Resources
    • Accendo Authors
    • FMEA Resources
    • Glossary
    • Feed Forward Publications
    • Openings
    • Books
    • Webinar Sources
    • Podcasts
  • Courses
    • Your Courses
    • Live Courses
      • Introduction to Reliability Engineering & Accelerated Testings Course Landing Page
      • Advanced Accelerated Testing Course Landing Page
    • Integral Concepts Courses
      • Reliability Analysis Methods Course Landing Page
      • Applied Reliability Analysis Course Landing Page
      • Statistics, Hypothesis Testing, & Regression Modeling Course Landing Page
      • Measurement System Assessment Course Landing Page
      • SPC & Process Capability Course Landing Page
      • Design of Experiments Course Landing Page
    • The Manufacturing Academy Courses
      • An Introduction to Reliability Engineering
      • Reliability Engineering Statistics
      • An Introduction to Quality Engineering
      • Quality Engineering Statistics
      • FMEA in Practice
      • Process Capability Analysis course
      • Root Cause Analysis and the 8D Corrective Action Process course
      • Return on Investment online course
    • Industrial Metallurgist Courses
    • FMEA courses Powered by The Luminous Group
    • Foundations of RCM online course
    • Reliability Engineering for Heavy Industry
    • How to be an Online Student
    • Quondam Courses
  • Calendar
    • Call for Papers Listing
    • Upcoming Webinars
    • Webinar Calendar
  • Login
    • Member Home
  • Barringer Process Reliability Introduction Course Landing Page
  • Upcoming Live Events
You are here: Home / Articles / Risk Prioritization in FMEA – a Summary

by Carl S. Carlson Leave a Comment

Risk Prioritization in FMEA – a Summary

Risk Prioritization in FMEA – a Summary

Every FMEA team needs to prioritize risk as part of the procedure. Why? Because companies or organizations have limited resources that must be focused on highest risk. The question becomes, by what method should we prioritize the risk identified in an FMEA?

Methods to prioritize risk in an FMEA

There are at least four methods to prioritize risk in an FMEA. These methods use different combinations of Severity, Occurrence, and Detection risk assessments. Quantitative Criticality Analysis uses additional calculations. All four methods have pros and cons.

1. SO Matrix or what is also called Qualitative Criticality Analysis
2. Action Priority Method
3. Quantitative Criticality Analysis
4. Risk Priority Number (RPN)

In the examples, I’ll use Severity, Occurrence and Detection scales that range from one to five.

SO Matrix or Qualitative Criticality Analysis

An SO matrix visually displays the severity risk on one axis and the occurrence risk on a second axis to show the level of overall risk. Colors, such as red, yellow, and green can be used to differentiate the corresponding risk.

[Note, the application of Qualitative Criticality Analysis in MIL-STD 1629A is the same as the application of SO Matrix in SAE J1739, albeit with different Severity and Occurrence scales.]

Example of SO Matrix for a Design FMEA.

Pros: It is simple and easy to use, and visually shows levels of risk.
Cons: It does not take into account detection risk; it does not consider quantitative data (if available).

Action Priority Method

The Action Priority (AP) method of risk prioritization accounts for all combinations of S, O, and D. This allows more emphasis on severity, and adjusts for the shortcoming in RPN (discussed below). The combinations for S, O, and D are represented in an Action Priority Table.

An AP table combines Severity (S), Occurrence (O), and Detection (D) ratings with suggested priority levels for identification of potential actions to reduce risk based on High (H), Medium (M), and Low (L) assessments. Individual companies may develop their own criteria for H, M, and L and make a company-specific Action Priority table available to the DFMEA team and customer or supplier.

The following is an example of a fictitious AP Table. AP Tables can also be tabular.

Pros: Accounts for all combinations of S, O, and D; resolves problem with RPN.
Cons: Is more complex than SO matrix.

Quantitative Criticality Analysis

Quantitative Criticality Analysis is unique to MIL-STD 1629A, or corresponding documents that are based on 1629A.

Excerpting from chapter 12 of Effective FMEAs:

Quantitative Criticality Analysis is a series of calculations to rank items and failure modes according to a formula covered below. To use Quantitative Criticality Analysis to evaluate risk and prioritize corrective actions:

1. Calculate the expected failures for each item. This is the number of failures estimated to occur based on the reliability/unreliability of the item at a given time.

2. Identify the mode ratio of unreliability for each potential failure mode. This is the portion of the item’s unreliability (in terms of expected failures) attributable to each potential failure mode.

3. Rate the probability of loss that will result from each failure mode that will occur. This is the probability that a failure of the item under analysis will cause a system failure. For example, in MIL-STD 1629A:

Actual Loss:      100%
Probable Loss: > 10% to < 100%
Possible Loss:  > 0% to < 10%
None:                 0

4. Calculate the mode criticality for each potential failure mode. This is the product of the three factors: Mode Criticality = Expected Failures (for the item) × Mode Ratio of Unreliability (for the failure mode) × Probability of Loss (for the failure mode).

5. Calculate the item criticality for each item. This is the sum of the mode criticalities for each failure mode identified for the item. Item Criticality = SUM of Mode Criticalities

The following is an example of Quantitative Criticality Analysis for a fictitious bicycle brake pad:

Risk Priority Number (RPN)

In an FMEA, Risk Priority Number (RPN) is a numerical ranking of the risk of each potential failure mode/cause, made up of the arithmetic product of three elements: severity of the effect, likelihood of occurrence of the cause, and likelihood of detection of the cause.

Once all high-severity issue have been addressed, the FMEA team can take up high RPN issues, in sequence. RPN thresholds are not advised.

Example: Power steering pump
(S, O and D scales are from 1 to 5)

Function: Delivers hydraulic power for steering by transforming oil pressure at inlet ([xx] psi) into higher oil pressure at outlet [yy] psi during engine idle speed

Failure Mode: Inadequate outlet pressure (less than [yy] psi)

Effect (Local: Pump): Low pressure fluid goes to steering gear
Effect (Next level: Steering Subsystem): Increased friction at steering gear
Effect (End user): Increased steering effort with potential accident during steering maneuvers

Severity: 5

Cause: Fluid incorrectly specified (viscosity too low)

Occurrence: 3

Prevention Control: Design guidelines for hydraulic fluid selection
Detection Control: Vehicle durability testing #123

Detection: 2

RPN: 30

Pros: Simplicity – a single number attempts to represent risk priority.
Cons: High severity must be addressed first before high RPN; RPN thresholds are enticing; actual risk is not linear.

See article: Is There a Better Way than RPN?

Next Article

The next article summarizes further insights into FMEA recommended actions.

[display_form id=415]

Filed Under: Articles, Inside FMEA

About Carl S. Carlson

Carl S. Carlson is a consultant and instructor in the areas of FMEA, reliability program planning and other reliability engineering disciplines, supporting over one hundred clients from a wide cross-section of industries. He has 35 years of experience in reliability testing, engineering, and management positions, including senior consultant with ReliaSoft Corporation, and senior manager for the Advanced Reliability Group at General Motors.

« What Are Best Practices for Facilitating Qualitative Assessments?
Risk And Safety »

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Articles by Carl Carlson
in the Inside FMEA series

[popup type="" link_text="Logo Info" ]

Information about FMEA Icon

Inside FMEA can be visually represented by a large tree, with roots, a solid trunk, branches, and leaves.

- The roots of the tree represent the philosophy and guiding principles for effective FMEAs.
- The solid trunk of the tree represents the fundamentals for all FMEAs.
- The branches represent the various FMEA applications.
- The leaves represent the valuable outcomes of FMEAs.
- This is intended to convey that each of the various FMEA applications have the same fundamentals and philosophical roots.

 

For example, the roots of the tree can represent following philosophy and guiding principles for effective FMEAs, such as:

1. Correct procedure         2. Lessons learned
3. Trained team                 4. Focus on prevention
5. Integrated with DFR    6. Skilled facilitation
7. Management support

The tree trunk represents the fundamentals of FMEA. All types of FMEA share common fundamentals, and these are essential to successful FMEA applications.

The tree branches can include the different types of FMEAs, including:

1. System FMEA         2. Design FMEA
3. Process FMEA        4. DRBFM
5. Hazard Analysis     6. RCM or Maintenance FMEA
7. Software FMEA      8. Other types of FMEA

The leaves of the tree branches represent individual FMEA projects, with a wide variety of FMEA scopes and results. [/popup]

Join Accendo

Receive information and updates about articles and many other resources offered by Accendo Reliability by becoming a member.

It’s free and only takes a minute.

Join Today

Recent Posts

  • Gremlins today
  • The Power of Vision in Leadership and Organizational Success
  • 3 Types of MTBF Stories
  • ALT: An in Depth Description
  • Project Email Economics

© 2025 FMS Reliability · Privacy Policy · Terms of Service · Cookies Policy